Customers Offshore crane manufacturer, USA

Every late supplier, chased before the buyer asks.

An offshore crane manufacturer in the USA builds lifting equipment from a long list of purchased parts. Elentaria now chases late suppliers, reads their replies and keeps the shared purchasing inboxes clear.

A desk with a monitor showing a technical drawing, a wall planner behind it
Built in
2 months
First-year value, est.
€138k
Systems
The company's ERP and shared mailboxes
Delivered as
Implementation partner, behind another company

The work as it was

Purchasing raised orders in the ERP and waited. Some suppliers confirmed the same day, some a week later with a new date, some not until a buyer ran the open order list and wrote to ask.

The shared purchasing inboxes carried everything else: confirmations, invoices, delivery notes, price lists, questions, filed by whoever had the inbox open. A reply could sit unread for days.

What was built

  1. 01

    Supplier follow-up

    Each morning Elentaria reads the open purchase orders in the ERP and writes, in the company's wording, to every supplier overdue by the agreed number of days.

  2. 02

    Reading the replies

    Each reply is read and the confirmed date recorded on the order. A reply that moves a date, splits a delivery or asks a question goes to the buyer.

  3. 03

    Clearing the shared inboxes

    Every email in the shared inboxes is classified by the rules purchasing set and filed or passed to the right workflow. What needs a person stays in view.

Reads
Open purchase orders in the ERP, and every email in the shared purchasing inboxes
Checks
Which orders are past the agreed confirmation window, what each reply changes, where each email belongs
Writes
The follow-up to the supplier, the confirmed date on the order, each email into its folder
To a person
Replies that move a date, split a delivery or ask a question, and emails the rules cannot place

One ordinary day

  1. 07:30

    The open order list is read from the ERP; follow-ups go out to every overdue supplier.

  2. 08:45

    Overnight replies are read. Confirmed dates go onto the orders; one supplier has moved a date.

  3. 09:00

    The buyer opens that order with the reply beside it, calls the supplier, records the outcome.

  4. 13:00

    A delivery note, an invoice and a price list arrive and are filed to their folders.

  5. 17:00

    Every follow-up, reply and filing is recorded against its order.

What changed

Buyers no longer run the open order list to find out who has gone quiet. The follow-up goes out on the agreed day, and the reply lands on the order.

A confirmation is on the order the day it arrives. The owner's estimate of the first-year value at this company's volumes, in hours saved, errors avoided and revenue protected, is €138k.

How it was delivered

Delivered as implementation partner behind another company that owned the client relationship, and live in two months. Rules first: when a supplier is chased, which replies a buyer sees, where each email belongs. The ERP was not changed and stays the system of record.

The same, for your workflow.

Bring one workflow the company runs by hand today to a live demo with the founders.